Block for Construction of CC Apron on PF No. 3 from 6th April, 2013 at Surat


The work of construction of CC Apron o­n PF no 3 at Surat Railway station will commence from 06.04.13 and will be completed by 04.06.13. Hence, a block will be taken at Platform No.3 at Surat during this period.

Due to the above block, following trains will be short terminated at Udhna station instead of Surat station :

Sr. No.
Train No.
Running between
1
59014
Bhusawal-Surat Passenger
2
13425
Malda Town-Surat Express
3
59052
Nandurbar-Surat Passenger
4
59026
Amravati-Surat fast Passenger
5
MEMU 69141
Sanjan-Surat MEMU
6
MEMU 69151
Valsad-Surat Memu
7
59037
Virar-Surat Passenger


Following trains will originate from Udhna station instead of Surat station :

Sr. No.
Train No.
Running between
Dep time from Udhna
1
59051
Surat-Nandurbar Passenger

18:40
2
MEMU 69142
Surat-Sanjan MEMU
17:35
3
MEMU 69111
Surat-Vadodra MEMU
17:40


A IInd class sleeper coach will be provided vice First Class coach in 59031/59032 Surat-Bharuch-Surat shuttle. Some long distance trains will be delayed by 5 minutes to 20 minutes due to the block. Passengers are requested to please take note of the above and cooperate with the railway administration.